DSA: Implement a scheduler that executes jobs with dependency constraints
Asked at
Boston Consulting Group
1Give yourself 5 minutes
2Answer out loud, not in your head
3Then compare with the answer below
0
Stuck? Show a way to structure it+
- 01State the contract and the key invariant for Dependency Scheduler
- 02Build prerequisite-to-dependent edges and indegrees
- 03Enqueue zero-indegree jobs
- 04Process and release dependents
- 05Report cycle if count is short
- 06Validate the result against boundary cases and state O(V + E) time and space
Reference answer
Then expect these follow-ups
Which invariant proves the Dependency Scheduler approach is correct?
Tests: correctness reasoning
What edge case would you test first?
Tests: follow-up reasoning